Which aspect should NOT be included in the functional program's financial requirements?

Study for the Examination for Architects in Canada (ExAC) Section 1. Enhance your knowledge with flashcards and multiple choice questions, each question comes with hints and explanations. Ace your exam preparation!

In preparing a functional program for an architectural project, it is essential to focus on practical and immediate financial requirements that relate directly to the execution of the project. This includes aspects such as the preliminary budget, construction costs, and fund allocation for specific community goals, all of which serve to guide the feasibility and operational aspects of the project.

Projected profits, however, are not typically included in the functional program's financial requirements because the primary focus of this document is to outline the scope, needs, and constraints of the project as it relates to planning and design, rather than to forecast financial performance or profitability. The functional program operates more on a basis of ensuring that the project meets its intended use and requirements, rather than providing a financial projection of potential revenue. Thus, incorporating projected profits would diverge from the primary aim of clearly defining the project's fundamental needs and operational framework.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy